wp775dfa92_1b.jpg
IRON
AND
COAL
wp8f722eef_1b.jpg

wpccc0174d_1b.jpg

wp084eaf12_1b.jpg

wp1dfe796c_1b.jpg

wpb94a9c27_1b.jpg

wp30c0080e_1b.jpg

wpe7f594fa_1b.jpg

wp41b60334_1b.jpg

wp28f83377_1b.jpg

wp58bd6e61_1b.jpg

wpf6d780f2_1b.jpg

wpa232f246_1b.jpg

wpb7de6eaf_1b.jpg

wpe25a4887_1b.jpg

wp8dd72539_1b.jpg

wp8a5a2b0d_1b.jpg

wp173b9717_1b.jpg

wpefe35af4_1b.jpg

wp18609ff9_1b.jpg

wpb4497c04_1b.jpg

wp8226ed8b_1b.jpg

wpd0fce529_1b.jpg

wpbf569d1c_1b.jpg

wpd6c1eaac_1b.jpg

wp170929bc_1b.jpg
wp7985112e_1b.jpg
wpe2b57e3a_1b.jpg
wpc8604a8e_1b.jpg
wp575ea45a_1b.jpg
wp344d603d_1b.jpg
Capital Outlay
£
Six boilers & nine economisers (making a total of nine boilers at the colliery which would be in use)
5,350
Alterations and renewals to No2 winding engine
1,200
Turbo electrical generating plant with motors, cables etc 1,200kW
15,000
TOTAL COST
21,550
Estimated Savings per annum
At boilers and economisers, coal consumption 5,500 tons @ 5/-
1,375
Reduction of coal due to introduction of electrical power. 12,000 @ 5/-
3,000
Reduction of labour for stoking,ashes, etc
2,000
Reduction on a/c of alteration to No2 winding engine
450
TOTAL SAVING
6,825